The First Stan Patrol 3007 for Bahamas at Damen Shipyards Gorinchem Picture: Damen |
|||
Damen has
designed the Stan Patrol 3007 to remain at sea for up to one week at a
time. To meet that requirement, they have provided on board accommodation
for a crew of 13, as well as a pantry and mess room. “Over a period
of approximately 15 weeks, we will install on board all machinery, electrical
installations, HVAC, navigational equipment, insulation and carpentry,”
states Mr Van der Zon. “After launching, sea trials and extensive testing will follow a commissioning period of approximately 5 weeks and the first Stan Patrol 3007 should be delivered in week 26 of 2015. After delivery, the crew of the vessel will undergo training in the Netherlands, before the vessel is shipped to the Bahamas,” says Mr Van der Zon. |
|||
First Stan Patrol 3007 Long range patrol vessel for Bahamas at Damen Shipyards Gorinchem